Waterproofing design, Project Management and Quality Assurance

Project Overview:

Weatherproof Consulting was commissioned to inspect and evaluate the existing water ingress and associated defects that were impairing the Hospital's operational capabilities, leading to consequential damage.

Key issues:

  • Water ingress impacting ICU, private suites, and common areas;

Project Objectives:

  • Identify the root cause(s) of the leak(s);

  • Develop a comprehensive and holistic rectification solution including a design and scope;

  • Manage the sequence of works;

  • Provide quality assurance including testing regimes to ensure the designed solution provided a fit for purpose end result

Design & Planning: To address the complex variables, our comprehensive planning included:

  • Conducting Facade testing with the use of a rain wand, inspection camera, smoke machine, infrared and moisture meters;

  • Performing a wind uplift study to establish the required termination points of several elements;

Implemented Solutions: To meet compliance and project objectives, we collectively applied the following:

  • Propping Solutions;

  • Proprietary cavity flashing system;

  • Wall tie type and spacing

  • Brick sizing;

  • Weep hole centres.

Conclusion:

Following our engagement, all water ingress issues outlined in our agreement have been fully resolved, enabling the hospital to continue its operations without interruption.